Finally, our long awaited slab was poured today.
After rain interruptions delaying progress, it's a relief to have the slab down.
A busy day with 7 workers on site, a pump truck and 3 concrete trucks on the go.
70 meters laid today.... at country (expensive) prices - $212 m3 for concrete, plus steel, pods, chairs, plastic and labour....you do the maths....puts a fair dint in the build budget lol
We are having step less walk in showers, so the pods in the shower areas were lowered (compared to the rest of the slab) to allow for this.